Bidders for the Shah gas development want longer to submit tenders

Contractors look for extensions at $10bn ADNOC JV
Contractors look for extensions at $10bn ADNOC JV

Reuters reported that contractors bidding on the project, a joint venture between the Abu Dhabi National Oil Company (ADNOC) and the US oil company ConocoPhillips, have been given different deadlines depending on which package they are bidding for.

“Officially we have not been informed of any extension, bids are going on,” one contractor is quoted by Reuters as saying.

“We are expecting an extension but we are not sure they will do it or not, competition is very harsh…The project will be extended a little bit,” another contractor told Reuters.

However, Ali al-Murar, senior vice president for support services at the joint-venture told Reuters that no contractor had asked for an extension and that the project was moving according to schedule.

When completed the Shah sour gas development is set to process 1 billion cubic feet per day of sour gas from 20 wells. ADNOC is the major shareholder with a 60% stake with ConocoPhillips holding the remaining 40%.

Deadline dates for major packages
(Source: Reuters)

Gas Gathering System: December
Processing plant: November 3
Sulphur recovery unit: November 3
Pipelines: November 4 (extended from Oct. 15)
Sulphur handling terminal: October 28
 