Topaz delivers LNG module to Qatargas

AdYard delivers $17 million Berth 6 LNG loading module for Qatargas

Topaz delivers LNG module to Qatargas
Topaz delivers LNG module to Qatargas

Topaz Energy and Marine’s Abu Dhabi subsidiary, Adyard, has completed the construction of Berth 6 LNG loading module for Qatargas.

The US$17 million project was awarded to Adyard by Fluor as a construction contract in January 2008. The project included the detailed engineering, fabrication and construction of module structures including installation of LNG tank, pumps and pipelines. The scope of work also included electrical and instrumentation work, cold insulation of pipelines and Epoxy fire proofing of the module.

The module will be transported to, and installed at the Ras Laffan Qatar Site in the first and second week of April.

Qatargas is in the process of developing an integrated LNG storage and loading facility at Ras Laffan Industrial City on the North-East coast of Qatar.

“This project success once again underscores Topaz’s ability of successfully and safely delivering large-scale, complex engineering projects,” said Fazel Fazelbhoy, CEO of Topaz Energy and Marine. “One of the key highlights of the project was the safe completion of 500,000 man hours without a lost time injury (LTI),” he added.
 