Habshan 5 gas project 90% finished, says GASCO

WAM agency reports Habshan 5 is 17 months ahead of schedule

Abu Dhabi Gas Industries (Gasco) announced that 90% of work on the Habshan 5 gas processing plant project was completed in May 2012.

The announcement was published on Sunday in “GASCO Image Magazine,” according to official state media agency WAM.

The report pointed out that this major feat had been accomplished in 33 months, well ahead of the 50-month contractual period for the project, which was slated fro commissioning in Q3 2013.

Gasco attributed the achievement to good business planning, management creativity and team work, reports WAM.

The Habshan 5 Process Plant is designed to process 1,000 million standard cubic feet per day (MMSCFD) of offshore gas from Umm Shaif and an additional 1,000 MMSCFD of onshore gas comprising of a mix of associated gas from ADCO and non-associated high sour gas from the Habshan fields.

Companies involved in the Habshan 5 project include JGC, Maire Tecnimont, Fluor (FEED), CCC, Descon and Kuwait’s Kharafi National.

 

 

Staff Writer